|
|
|
Case
Studies
|
|
|
|
CASE #1:
Planning and re-engineering with AutoMod
|
|
The demand is very dynamic, our production is
increasing, and all our customers insist on
being supplied Just In Time.
|
Situation:
This company has plants in Japan, the United States and Canada. It is a supplier of
components for the automotive industry and counts the major players in this industry
among its customers. After stamping and welding operations, the products are loaded
onto a Power & Free Conveyor to be carried from the manufacturing area towards the
painting and chemical coating rooms where are treated after being automatically
transferred on a chain conveyor. When they leave the area, they are loaded onto the
Power & Free Conveyor and directed into the stock room before they are sent to the
final assembly and shipping area where they are unloaded from the conveyor. The total
cycle time is longer than the expected response time required by the customers. Also,
the demand is very dynamic and orders are changed frequently, so the company must
maintain a significant inventory of WIP between the paint and the assembly area.
Problem:
With such a dynamic demand and a forecasted new increase in the production, how will it
be possible to reconfigure the Power & Free Conveyor, the backbone of the entire
plant, so that we can the same time minimize our WIP and improve the response time to
our customers?
Solution:
Accurate 3D simulation with the ability to represent P&F and chain conveyors was a
prerequisite to answer this question. This is why AutoMod was chosen. The model
developed by MultiCIM is focused around the conveyors systems (P&F and chain
conveyor). AutoMod has allowed us to represent both the complex logic and the detail up
to the level of individual components being loaded on racks. Up to two months of
detailed production forecasts can be simulated within minutes. Once validated against
real-life results, this model has been used to demonstrate the interest on
reconfiguring critical areas of the conveyor systems.
Among the scenarios tested, the addition of spurs sections at the loading booths showed
an improvement of 12% on the response time for the concerned parts. The model did not
show significant improvements in the throughput when the same approach was tested at
the unloading stations, proving that this would have been an unnecessary investment. On
another hand, the simulations demonstrated that the company should consider changing
the organization of the stock area before assembly, as some scenarios proved its layout
not to be as efficient as it could have been, thus forcing the company to maintain a
higher WIP than necessary to achieve the required level of service. After quantifying
the impact of various changes on the system's performance, the model was enhanced to
include a proposed addition for the production of a new product line and validate the
new P&F conveyor layout. Finally, due to the flexible approach used to develop the
model (external data files edited through Excel), it has been utilized since by the
company for testing and validating new planning and mix strategies.
|
|
CASE #2: Validating an automated conveyor system with AutoMod
|
|
Can we ship 3,500 orders in 8 hours (vs. 1,900 today) with our new and fully
automated conveyor system?
|
Situation:
This company which specializes in 24hr office product on-site delivery has forecasted
an increase in its demand in the next months. In order to be able to cope with it, it
has just bought and installed a new fully automated conveyor system
(PLC driven,
photocell and scanner controlled, with scales etc.). This conveyor is in charge of
circulating totes around the picking zones where employees are loading them with the
appropriate quantity of the required items. Once an order is fulfilled, the tote is
sent to an inspection and packaging counter where its contents is controlled and sent
to the shipping dock while the empty tote is sent back into the loop (if necessary).
Problem:
Proving to be perfectly efficient at the current level of activity, how can we make
sure the system will be able to deal with a 75% increase on the demand ? This question,
despite the optimism of the conveyor manufacturer, was still an issue for the company
which started to perform on-site simulations (!). But after some time (8 hours) and
money consuming (hiring personnel to operate the system during the night) simulations
of this sort the question was still unanswered.
Solution:
Due to its built-in expert material-handling modules, AutoMod was a perfect candidate
to help the company answering this question. Within a day the entire layout and
characteristics (speed, type of section, orientation end dimensions) of the conveyors
were reproduced into AutoMod. The control logic and picking and control activities were
added to the model and MultiCIM started testing demand scenarios against different
configurations of the system. Once validated with the company and the conveyor
supplier, within minutes, the AutoMod model was able to run an entire production shift
of 6 to 11 hours (depending on the scenario) and was also giving more insight on the
behavior of the system than the company had been able to obtain so far using other
means. These statistics include the time in system, re-circulation rate, average hourly
input and output, time in zone, average number of totes in zone, operators utilization
as well as sections' specific statistics for the conveyor.
The simulations demonstrated that the system was not capable of handling the workload
of 3,500 orders per day in less than 8 hours but rather in some 11 hours. But against
all expectations, the major bottleneck was not really a specific area of the conveyor
but rather the organization of the activities in the picking zones. As the totes were
admitted by batches of 10 initially, the re-circulation rate and the time in system
were very high. By making the picking a more fluid activity (i.e. batch of 1), an
improvement of 30% on the original productivity was observed.
After this first result, different configurations were tested with various demand
scenarios to find out the appropriate organization for each level of demand allowing
the company to be aware of other potential bottlenecks. The model was also used to
validate some aspects of the PLC's programs to enhance the routing of the totes on the
conveyor.
|
|